Minutes of the 76th MTE meeting held on Thursday May 23rd 2013

Present :

R. Fernandez Ortega, J. A. Ferreira Somoza, S. Gilardoni, M. Giovannozzi, M. Hourican, S. Mataguez.

Excused :

S. Damjanovic, P. Demarest, C. Hernalsteens.


Main items

Conclusions and actions from the meeting
     
  1. Final layout of the shielding for the dummy septum:

    • The longitudinal dimension of the top block should is 900 mm to avoid any interference with the ion pump.

    • D. Bodart confirmed that the new bus bars have the same overall size as the current ones.

    • Integration (with PS ring and dummy septum) has been checked: a longitudinal displacement of the downstream wall should be applied at construction time.

    • Next steps:

      • An EDMS approval should be set-up to collect the comments quickly, i.e., a week of time (Action: Mike).

      • Information concerning the manufacturing delay and costs should be provided (Action: Raul and Eliseo).

      • After the completion of the FLUKA simulations a decision will be taken as of the layout of the shielding to be installed in SS75 (Action: Simone).

  2. Overall planning: 

    • The schedule of the dummy septum construction and installation has been provided.

    • Next steps:

      • Include activities from: vacuum and transport (Action: Simon).

      • Include activities from: BI, civil engineering, impedance measurements (Action: Mike).

  3. Next steps:

    • Review radiation simulations and intervention times to allow establishing official figures concerning radiation doses (Action: Sanja).

    • Prepare for writing a detailed report of the dummy septum activities. The structure will be prepared and distributed (Action: Massimo).

 

   