MTE Actions

Uncompleted Actions

Completed Actions

 

Uncompleted Actions

Action number, Responsible(s), description

Discussed

Status

   

 top  |  index 

 

 

 

 

Completed Actions

Action number, Responsible(s), description

Discussed

Completed

Action 080925_1   by T. Fowler and L. Sermeus

Find a solution for the DFA242 switch

#37  2008 Sep 25 to be reported
Action 080410_1   by A. Franchi

Evaluate the impact of different bumpers' rise-times (bump 16) on the beam orbit

#29  2008 Apr 10 #30  2008 Apr 24
Action 080410_2   by C. Dehavay & J.-M. Cravero

Testing the bumper magnets' controls (bump 16)

#29  2008 Apr 10 #30  2008 Apr 24
Action 080410_4   by C. Dehavay & G. Metral

Evaluate the possibility of having separate forewarning signals for the bumper magnets (bump 16)

#29  2008 Apr 10 #30  2008 Apr 24
Action 080410_3   by S. Gilardoni

Agree with AB/OP for testing the dual-mode operation of the BFA9 during the hardware tests.

#29  2008 Apr 10 #30  2008 Apr 24
Action 080313_1   by R. Brown & R. Principe

Update the distribution list for the meetings and the minutes on the hardware tests

#28  2008 Mar 13 #30  2008 Apr 24
Action 080219_1 by A. Franchi
Check vertical trajectory in the TT2 line due to the tilted installation of the magnetic septum
#26 2008 Feb 19 #27 2008 Feb 28
Action 080131_1   by R. Steerenberg
Protection measures against failures of the MTE
#25 2008 Jan 31 #26 2008 Feb 19
Action 080116_1   by C. Dehavay
Complete MTE controls and signals nomenclature
#24 2008 Jan 16 #26 2008 Feb 19
Action 071219_1   by A. Franchi

Check the kicker polarities

#23 2007 Dec 19 #24 2008 Jan 16
Action 071105_1   by J.-M. Cravero

Bump 16 installation strategy

#19 2007 Oct 26 #21 2007 Nov 22
Action 071026_1   by A. Franchi

Naming of the new MTE non-linear elements and of the bumper magnets (bump 16)

#19 2007 Oct 26 #21 2007 Nov 22
Action 071026_2   by E. Mahner

Comment the non-conformity of the new special bellows.

#19 2007 Oct 26 #20 2007 Nov 05
Action 071004_1   by J.-M. Cravero

Estimate the inductance of the cables for the bump16

#18 2007 Oct  4 #19 2007 Oct 26
Action 070913_1   by A. Beuret

Check the reliability of the octupole TEKELEC power converter

#17 2007 Sep 13 #18 2007 Oct  4
Action 070913_2   by A. Beuret

Check that the octupoles and sextupoles power converters have an analog output for the samplers

#17 2007 Sep 13 #18 2007 Oct  4
Action 070802_1   by D. Bodart, T. Zickler, R. Brown

Check the clearance of a spare magnet for the new vacuum chambers

#15  2007 Aug 02

#18 2007 Oct  4
Action 070524_3   by E. Mahner

Define the procedures for vacuum tests (vacuum chambers and the bellows)

#12  2007 May 24

#17 2007 Sep 13
Action 070607_3   by E. Mahner

Perform leak tests on the three chambers found on top of the PS tunnel

#13  2007 Jun 07

#17 2007 Sep 13
Action 070524_2   by M. Caccioppoli

Fix the date for the delivery  of the bellows

#12  2007 May 24

#15 2007 Aug 02
Action 070607_1   by M. Caccioppoli

Check the weld procedure at ZANON (chambers MU14/15/16)

#13  2007 Jun 07

#15 2007 Aug 02
Action 070607_4   by G. Villiger

Update the list of spares and items to be built for MTE activities

#13  2007 Jun 07

#15 2007 Aug 02
Action 070524_4   by M. Caccioppoli

Follow up the production of the new flanges

#12  2007 May 24

#14 2007  Jul 05
Action 070607_2   by T. Fowler

Definition of details for connecting the ion pump on the kicker tank

#13  2007 Jun 07

#14 2007  Jul 05
Action 070607_5   by M. Giovannozzi

follow up the issue of new smaller vacuum chamber in SS15

#13  2007 Jun 07

#14 2007  Jul 05
Action 070524_1   by G. Villiger

Check tolerances in the manufacture drawings (chambers MU14/15/16)

#12  2007 May 24

#13 2007 Jun 07
Action 070524_5   by G. Villiger

Evaluate from simulation the deflection of the transition piece between BFA21 and KFA21 + evaluate the possibility of a support

#12  2007 May 24

#13 2007 Jun 07
Action 070524_6   by E. Mahner

Prepare a cost estimate for the mobile vacuum group (for testing the kicker tanks)

#12  2007 May 24

#13 2007 Jun 07
Action 070524_7   by G. Villiger

Perform simulations for the modification of the PS kickers vacuum tanks

#12  2007 May 24

#13 2007 Jun 07
Action 061207_1   by A. Franchi

Change of the DFA243 name.

#5  2006 Dec 07

#7  2007 Feb 01

#10 2007 Apr 26
Action 061102_4   by A. Beuret

Verify during the SD 2006/7 together with the AB/PO specialists the reliability of the TEKELEC power converters (octupoles)

#2  2006 Nov  2 #9  2007 Mar 29
Action 061123_1   by J. Monteiro

Include the deadlines for the installation of controls in bldg. 367 (June 2007) and the chambers production in the SD 2007/8 schedule

#4  2006 Nov 23

#8  2007 Mar 01
Action 070118_1  by T. Zickler

Replace the cards of the passive compensation of eddy currents in MU18 and 19 with the version compatible with the enlarged, but standard vacuum chamber.

#6  2007 Jan 18

#7  2007 Feb 01
Action 061102_5   by G. Villiger

Definitions of the workshop activities related to the MTE for the SD 2006/7

#2  2006 Nov  2

#4  2006 Nov 23

completed
Action 061207_2   by R. Principe

Check the feasibility of the coexistence between LEIR and the MTE power converters in the South Hall in 2008 (cooling)

#5  2006 Dec 07

#6  2007 Jan 18
Action 061123_2   by E. Mahner

Provide (to C. Rossi) the details of the conical transition from MU07 to the upstream side of the 80 MHz RF cavity.

#4  2006 Nov 23

#6  2007 Jan 18
Action 061102_1   by A. Beuret

Investigate the possibility of installing the new power converters for the octupoles in the SD 2007/8 (budget)

#2  2006 Nov  2

#3  2006 Nov  9

#5  2006 Dec 07
Action 061102_3   by A. Beuret

Check the deadline for the removal of the the existing power converters platform imposed by Linac4 and LEIR

#2  2006 Nov  2

#4  2006 Nov 23

#5  2006 Dec 07
Action 061102_6   by G. Villiger

Provide to  T. Dobers the drawings of both the new octupoles and the modified TT2 line as soon as they are available for alignment

#2  2006 Nov  2 #5  2006 Dec 07

#6  2007 Jan 18

Action 061102_7   by F. Di Maio

Verify the intervention on the controls necessary for the relocations of the RF cavity and sextupoles during the SD 2006/7

#2  2006 Nov  2 #4  2006 Nov 23
Action 061109_1   by F. Di Maio

Check the deadline for the installation plan of UPS, network, and controls cables in building 367 related to the kickers (SD 2007/8)

#3  2006 Nov  9 #4  2006 Nov 23
Action 061109_2   by T. Fowler

Notification to the people responsible for the safety and the  environmental protection of the latest installation layouts (Bld. 367 & 359) related to the kickers

#3  2006 Nov  9 #4  2006 Nov 23
Action 061109_3   by T. Fowler/E. Page

Check whether some vacuum pumps need to be moved together the ERD DAF243 in TT2 (SD 2006/7)

#3  2006 Nov  9 #4  2006 Nov 23
   