Minutes of the
57th MTE meeting held on Thursday May 10th 2012
|
Present :
S. Damjanovic, M. Giovannozzi, C. Hernalsteens
|
Excused :
J. Borburgh, M. Hourican, S. Gilardoni
|
Main items
Conclusions and actions from
the meeting |
-
The drawings of the PS main magnet
vacuum chambers have been provided to Sanja.
-
The option of installing shielding
upstream of the dummy septum has been analysed: it
provides a reduction of about a factor of 2.5 on the
dose delivered to the MMU14. However, it increases the
dose delivered to MMU15 by a factor 1.2. The dose
delivered to the coils of the MMU15 is of the order of
1MGy: it should be evaluated by magnets experts (Action:
TE-MSC).
-
Details for the tracking of particles
have been discussed and a set of input file will be
prepared (Action: DGS-RP and ABP).
|
|
|