Minutes of the 71st MTE meeting held on Thursday February 28th 2013

Present :

 S. Damjanovic, R. Fernandez Ortega, M. Giovannozzi, M. Hourican, J.-M. Lacroix.

Excused :

J. Borburgh, P. Demarest, C. Hernalsteens.


Main items

Conclusions and actions from the meeting
     
  1. The design of the shielding has been reviwed:

    • A special block will be built with holes for the manual system to move the blade in case of major failure.

    • The changes on the base of the shielding (according to the requests of transport experts and magnet experts) are not relevant for radio protection and are approved.

    • All the blocks are concrete blocks apart from three that are marble blocks. The presence of lifting points for the marble blocks should be checked (Action: Raul).

    • Next steps:

      • The final layout in 3D will be circulated by end of next week (Action: Raul).

      • All people concerned should provide feedback and comments (Action: All).

      • In parallel the analysis of avaialbility of blocks will be carried out (Action: Raul).

      • The 3D model of the dummy septum will be integrated in the shielding layout to ensure full compatibility (Action: Raul, Mike).

  2. Other activities: 

    • A formal EDMS approval round of the septum laytou will be launched (Action: Mike).

    • A schedule of the various activities, including also installation, will be prepared (Action: Mike). This will enable RP to analysis the IMPACT activity.

    • A formal EDMS approval round is also foreseen for the shielding layout (Action: Raul).

 

   