Minutes of the
72nd MTE meeting held on Thursday April 4th 2013
|
Present :
S. Burger, S. Damjanovic, P. Demarest, R. Fernandez Ortega, S.
Gilardoni, M. Giovannozzi, M. Hourican,
J.-M. Lacroix, S. Mataguez, J. Vollaire.
|
Excused :
D. Bodart, J. Borburgh, C. Hernalsteens.
|
Main items
Conclusions and actions from
the meeting |
-
The design of the shielding has been reviewed:
-
Most of the blocks are now special in order
to optimised the layout.
-
The length of the shielding has been reduced
to 980 mm.
-
Four blocks are marble blocks.
-
Next steps:
-
Check that the efficiency in terms of
radioprotection is still acceptable. In particular, the
thickness of the side wall reduced to 200 mm and the
increased opening in the downstream part of the shielding
should be checked in detail (Action: Sanja).
-
Check that the length can be increased to
1000 mm without any impact on magnet access and installation (Action:
Raul).
-
Check that the main magnet bus bars are
accessible and that an additional overhang of 100 mm/200 mm
would be acceptable too (Action: Raul).
-
Check that the transport endorses the
proposed layout (Action: Raul).
-
Other points:
-
Jean-Michel checked the overall integration:
-
The overall installation activity will be
provided to Simon in order to be included in the LS1 general
planning (Action:
Mike).
-
Massimo reported that additional checks
performed by S. Persichelli and B. Salvant showed that the line
at 100 MHz recently observed in the simulations of the dummy
septum impedance was also presented in the original design. Two
possible solutions are at hand:
-
Mike comments that both are feasible and
should not pose any problem. In this case the first solution
would be the preferred option (Action: Mike, Serena,
Benoit).
-
The BTV construction is progressing well and
no issues are foreseen, so far. It is important to verify that
the integration of the BTV is compatible with the new layout of
the shielding (Action: Stephane).
|
|
|