77th MTE meeting held on Thursday May 30th 2013
|
Present :
S. Burger, S. Damjanovic, M. Giovannozzi, M. Hourican, S. Mataguez.
|
Excused :
S. Gilardoni, C. Hernalsteens, B. Salvant.
|
Main items
Conclusions and actions from
the meeting |
-
Final layout of the shielding for the
dummy septum has been described in an EDMS document for approval:
-
The new layout has been compared with the
previous one in terms of radio protection and the differences
are minor. So the final layout can be approved as far as RP
aspects are considered.
-
The fact that the flanges will be removed
with the shielding in place has reduced the dose delivered to
personnel by a factor of two.
-
Next steps:
-
All people in the approval list are asked
to comment the EDMS document as soon as possible (earlier
than Wednesday 5th of June) such that constriction can be
launched as soon as a quoting is received (Action:
All).
-
The detailed situation of the dose
delivered to personnel in case of interventions should be
reviewed before performing the final computations: septum,
vacuum, and instrumentation experts are requested to confirm
or provide additional information with respect to the
details already provided (Action: Mike, Stephane,
Paul).
-
Overall planning:
-
News from the beam instrumentation:
-
The device has been received from the
workshop and tested.
-
It works fine for pushing the screen in the
in beam position.
-
It has some difficulties in removing the
screen out of the beam position. This seems to be due to a too
high friction. The situation is being investigated in details
and it is hoped that the friction can be reduced by an extended
testing cycle.
-
At the IEFC next week the proposed changes to the
PS ring will be presented for formal approval and then an ECR will
be prepared and circulated (Action: Massimo).
-
Next steps:
|
|
|