Minutes of the
80th MTE meeting held on Wednesday August 7th 2013
|
Present :
S. Burger, S. Damjanovic,
J. A. Ferreira Somoza, S. Gilardoni, M. Giovannozzi, M. Hourican.
|
Excused :
S. Mataguez.
|
Main items
Conclusions and actions from
the meeting |
-
Dummy septum status:
-
The construction is progressing well. The
non-conformity of the downstream vacuum chamber (vertical
dimension of 69 mm instead of 70 mm) will be corrected.
According to the schedule, Mike should visit the firm next week
and the tank should be delivered to CERN the week after.
-
The controls for the dummy septum are under
the responsibility of TE-ABT and should be made available by the
hardware tests period of the PS (Action: Mike).
-
Shielding:
-
The concrete blocks have been received in
Prevessin.
-
The top block will be delivered by
end-September or beginning of October, due to the need of a
special lifting hook.
-
The preparation of the base block and of the
lateral block to enable the use of the crank system will be done
in the coming weeks under the supervision of Mike.
-
The possibility of a test assembly should be
envisaged (Action: Massimo to discuss with Raul,
Caterina and Mike).
-
BTVP:
-
The AP agreed to deliver the components by
end of August.
-
The whole mechanism has been reviewed by
vacuum experts: no major issues have been found. The important
point is to information the PS vacuum specialist s of the
presence of a vacuum enclosure linked with the moving mechanism
of the BTV: in case of leaks a detection of this vacuum
enclosure should be performed. The tests performed so far will
be analysed by vacuum experts and a report prepared (Action:
Stephane, Nicholas, José Antonio).
-
The parking position of the BTV screen for
all positions of the dummy septum blade should be evaluated in
order to exclude that the screen might remain in beam (Action:
Mike, Stephane).
-
The controls for the BTVP are under the
responsibility of BI and should be made available by the
hardware tests period of the PS (Action: Stephane).
-
Two contributions for the final report have been
received. It is reminded that the missing contributions should be
sent by end of August (Action:
All). Final editing will start soon afterwards (Action:
Massimo)
|
|
|