Minutes of the
81st MTE meeting held on Thursday August 29th 2013
|
Present :
D. Bodart, S. Damjanovic,
P. Demarest, M. Giovannozzi, N. J. Jurado, S. Mataguez, M. Hourican, J.
Vollaire.
|
Excused :
C. Hernalsteens.
|
Main items
Conclusions and actions from
the meeting |
-
Dummy septum status:
-
The vacuum chambers are ready and should be
delivered at CERN by next week.
-
The vacuum tank should be delivered at CERN
also next week.
-
Assembly should start by mid-September and
should be completed by end of October.
-
Shielding:
-
The block are already built and at CERN
(close to the Prevessin BBQ area), apart from the top block.
-
A place to store them in the PS ring is
available.
-
Next week, at the latest, the base block will
be prepared. At the same time the 60 mm diameter openings in the
later block will be drilled.
-
The best location for the mockup is just
outside PS door 102. Currently, some coils are stored there, but
a proper storage area is already available on the top of the PS
shielding. Transport will be contacted to organise the move of
the coils, the move of the blocks from Prevessin, and the
construction of the mockup (Action: Dominique).
The status of the nearby crane should also be checked (Action:
Simon).
-
It is communicated that no extension of the
side wall will be needed.
-
BTV:
-
The AP will deliver the components by
mid-September. This is two weeks later than the original
planning, but it should not be a big problem.
-
The BTV should be assembled and installed in
the dummy septum before end of October.
-
Installation schedule:
-
According to the current version of the PS
schedule, the dummy septum should be installed starting on
12/12.
-
One month before the installation activities
a global IMPACT should be made available (Action: Mike
and Simon).
-
A safety file should be prepared: details
will be checked with Rende (Action: Massimo).
-
In total three contributions for the final report have been
received. It is reminded that the missing contributions should be
sent by mid-September (Action:
All). Final editing will start soon afterwards (Action:
Massimo)
|
|
|