Minutes of the
83rd MTE meeting held on Thursday October 10th 2013
|
Present :
S. Burger, S. Damjanovic,
M. Giovannozzi, N. J. Jurado, M. Hourican.
|
Excused :
S. Gilardoni, C. Hernalsteens, S. Mataguez.
|
Main items
Conclusions and actions from
the meeting |
-
Dummy septum status:
-
The assembly activities are progressing well.
-
A vacuum acceptance test has been performed.
P. Demarest confirmed the need to additional cleaning, which is
on-going.
-
Shielding:
-
The shielding has been assembled in the PS
tunnel closed to the door 102. See
here.
-
The position of the hook for the base block
is not at the location of the CG of the block: compensatory
measures will be taken (Action: Mike).
-
The availability of the top block should be
checked (Action: Massimo).
-
BTV:
-
The assembly activities are progressing well.
-
The spare BTV will require an optimised
designed, based on the experience of the current device.
-
Overall schedule:
-
In two weeks the BTV should be ready for
installation in the dummy septum.
-
Impedance measurements should be planned.
Hardware for supporting the wire is ready. More details
concerning the dates are expected by beginning of next week (Action: Mike
and Massimo).
-
To date, the original installation date, 12
of December, is maintained: the various activities are all on
time.
-
A specific IMPACT and DMR for the installation of
the dummy septum are required and should be prepared (Action:
Mike).
|
|
|